As the calendar turns to 2023…
We anticipate the final wrap-up phase of UUCV’s long journey with our Capital Campaign. The campaign has progressed through: visioning and planning in 2017, a pledge drive in 2018, and years of completing the identified projects (delayed by COVID-19 and supply chain issues). We are nearing the finish line! We encourage long-time members and new attendees to remember or learn about our congregation’s commitment and the significant improvements accomplished by this Capital Campaign.
Let’s celebrate the Capital Campaign’s accomplishments:
December 2018 – Expanded the DLFD position to full-time
October 2019 – New roof installed over the social hall and porches
February 2020 – New replacement windows throughout most of the church
March 2020 – The impact of COVID-19 paused project work for months
October 2020 – Masonry work: repointed brick, rebuilt exterior wall & stairs
Summer 2021 – Replaced exterior doors and upgraded entrance security
– New and remodeled accessible bathrooms on both levels
– New hospitality and custodial rooms and an expanded main lobby
– New enhanced lighting in the lower level hall and main lobby
– Exterior painting and replacement soffits and gutters
February 2022 – Upgraded kitchen electrical systems and new appliances
August 2022 – Redesigned the main drive-up entrance for accessibility
– Repaved the parking lot
Final goals still to be accomplished:
*Repair and paint the steeple
*Paint the exterior arches over sanctuary windows and doors
*Create an activity/play area on the side yard
*New members and friends of UUCV we invite you to join in financially supporting the Capital Campaign. This can be done as a one-time donation or a few payments. Additional donations will help UUCV reach the finish line. Please write “Capital Campaign” on the memo line of your checks. For more information contact the church office (717-249-8944 or office@uucv.net)